Project
Charlotte Douglas International Airport
Concourse A Renovation
Project Location
Charlotte, NC
Industries
Aviation, Cultural & Community
Services
Construction Management, Preconstruction, Virtual Construction
Square Footage
54,996 (Renovation) 10,445 (New)
Schedule Duration
17 months
Charlotte Douglas International Airport Concourse A Renovation
Scope
Concourse A Renovation included a complete overhaul of all floor, wall and ceiling finishes throughout the concourse. The project was phased in order to maintain operations within the concourse throughout construction
Highlights
Upgrades were completed to the fire sprinkler system, HVAC and fire alarm systems
Two passenger boarding bridges were relocated and the building was expanded in two locations, totaling approximately 10,000 square feet
A jet fuel line and jet fuel pit were installed on the ramp