Prisma Health Greenville Memorial Hospital – Diagnostic & Treatment Pavilion

Scope

  • Addition to the existing hospital with five floors of shell space over the existing loading dock

  • Complete interior upfit and renovation of the existing lab

Challenges

  • To prevent the existing loading dock from being relocated, the project was designed to span the dock, but allow room for trucks to drive underneath. This required the unique steel structure that hung from trusses, rather than resting on a conventional column foundation

  • The complex structure, unusually tight confines of the site, and the ongoing operations of two loading docks made scheduling a challenge. Early release of the site and steel packages allowed work to begin at the earliest possible date. Use of strategic combinations of trade packages, such as earthwork and utilities work, maximized efficiency