Project

Nash UNC Health Care
Hospital Parking Deck and Central Energy Plant

Project Location

Rocky Mount, NC

Industries

Healthcare, Parking Decks

Services

General Contracting, Preconstruction

Square Footage

158,000 (Parking Deck), 15,300 (Central Energy Plant)

Schedule Duration

9 months (Parking Deck) 11 months (Central Energy Plant)

Nash UNC Health Care Hospital Parking Deck and Central Energy Plant

Scope

  • Parking deck is a 411-space, cast-in-place, post-tension concrete structure built for hospital visitors, staff and physicians

  • New 15,300-square-foot plant incorporates three boilers, four chillers, four cooling towers, two 30,000-gallon fuel tanks, and a 1250-KW generator

Challenges

  • Project was brought online while existing hospital physical plant services were renovated, relocated and maintained